Planning Guide

How solar installation works in Australia

An installer in a safety harness fitting solar panels to a tin roof

Your solar rebate, checked before you sign

WST

By Why Solar Team

Find out what your home actually needs

Published . Updated . Checked on 27 October 2026.

Solar installation is the process that takes a system from a signed quote to switch-on: choosing an installer, getting the network connection approved, installing the panels and inverter, testing, and confirming the meter. The installation itself takes 1 to 3 days, according to energy.gov.au, but switch-on can wait for the network connection and the smart meter. Order and timing vary by state and network. The Australian Government's Solar for households guide sets out getting solar in seven steps, and this guide covers the installation part. To start with a quote, see how Why Solar matches you with an installer.

How solar installation works, step by step

  1. Choose an accredited installer and get quotes. energy.gov.au suggests quotes from at least 3 suppliers and a site visit, which makes it more likely that switchboard, roof access, inverter location and shading issues are picked up. Ask for the installer's accreditation number. Solar Accreditation Australia (SAA) accredits individuals, not companies, and offers a way to check whether an installer holds accreditation. The buying solar guide covers what to compare.
  2. Agree the quote and contract. Read the contract, check for a cooling-off period or exit fees, and ask for any claim a representative made to be written in.
  3. Network connection application. Your retailer or installer lodges it with your distribution network service provider. In most places it needs approval before installation.
  4. Switchboard or meter board work. Any upgrade is usually done before the solar installation starts.
  5. Installation. It takes 1 to 3 days, depending on the size of the system and the complexity of the job.
  6. Testing, commissioning and paperwork. The installer tests the system, completes a certificate of electrical safety or compliance and signs a written compliance statement. Some states add an independent inspection.
  7. Smart meter installed or configured. With solar you need a smart meter, and in most states your electricity retailer arranges it.
  8. Switch-on once confirmed. Wait for confirmation that the smart meter is installed or configured before you switch the system on.
  9. STCs created. A registered agent or you create small-scale technology certificates within 12 months of installation.

The order varies by state, so your installer's sequence may differ from this list. The next section sets out the time frames that each source states.

Find out what your home actually needs

Free, takes 60 seconds, no obligation.

Timeline from quote to switch-on

No single timeline applies from signing to switch-on. It depends on your network, your state and the smart meter. The table lists only the time frames each source states, as at 27 October 2026.

Network or stateStageTime statedSource
All statesInstallation1 to 3 daysenergy.gov.au
Some areasConnection agreementUp to 30 business daysenergy.gov.au
NSW, Ausgrid network areaApproval of small residential systems that meet standard requirementsAutomatic. If you have not heard within 10 business days, contact AusgridAusgrid
Qld, EnergexBasic connection offer, if not expeditedWithin 10 business days, then 45 business days to acceptEnergex
Qld, EnergexNegotiated connection offerEnergex aims for 65 business days, then 20 business days to acceptEnergex
Vic, AusNet network areaCertificate of Electrical Safety organised by your installerWithin eight business days of installationAusNet
VicInstaller lodges the Certificate of Electrical Safety and arranges an independent inspectionWithin 10 daysenergy.gov.au
WA, Horizon Power network areasNotice of completionWithin three days of installationenergy.gov.au

In Queensland, Energex says installation must not start until you have accepted the connection offer and the contract has been formed. Ask your installer which stage your system is at and what you are waiting on.

Approvals and paperwork: network connection, accreditation, STCs and council

Most of the paperwork is handled by your installer or retailer, but a system cannot be switched on until the network and meter steps are done.

Network connection

A connection agreement with your distribution network service provider (DNSP) is needed before the system can connect to the grid. It includes any network limit on inverter size or on how much electricity you can export. You cannot choose your DNSP. Its name is under "Faults and Emergencies" on your electricity bill. The rules differ by state and by network, as at 27 October 2026. Unless a network operator is named, the detail below comes from energy.gov.au.

  • NSW, Ausgrid network area: according to Ausgrid, your installer manages the approval in most cases, and small residential systems that meet standard requirements are automatically approved. Other NSW networks have their own processes, so ask your network operator or installer.
  • Victoria, according to energy.gov.au: your retailer or installer lodges the network connection application before installation. After installation the installer lodges a Certificate of Electrical Safety with Energy Safe Victoria and arranges an independent inspection within 10 days, then lodges paperwork so the smart meter is configured. AusNet, which serves part of Victoria, says your installer should organise the Certificate of Electrical Safety within eight business days of installation. Both describe the same post-installation step, so ask your installer which timeframe applies to you.
  • Queensland, according to energy.gov.au: your retailer or installer lodges the network connection application, and it needs approval before installation. This may take longer for regional customers and a technical assessment may be required. After installation the installer lodges an Electrical Work Request (Energex customers) or Form A (Ergon customers).
  • South Australia, according to energy.gov.au: your retailer or installer lodges the network connection application with SA Power Networks, which in South Australia is the Small Embedded Generator (SEG) request form. Once it is approved, your retailer or installer sends the SEG request form to your electricity retailer, who then arranges the smart meter. A meter isolator may need to be fitted first, so the system is sometimes installed before the smart meter.
  • Tasmania, according to energy.gov.au: the installer gives technical information to TasNetworks and a Certificate of Electrical Compliance to Tech Safe Tasmania, which does an independent inspection.
  • ACT, according to energy.gov.au: most systems need no development approval. The installer applies to Evoenergy for a special connection request, and Access Canberra may inspect after switch-on.
  • Northern Territory, according to energy.gov.au: for inverters up to 30 kW the installer lodges a connection agreement with Power and Water. Above 30 kW a different process applies.
  • Western Australia, according to energy.gov.au: the installer applies through the electricity retailer, usually Synergy, and the embedded generation connection is approved before installation. Horizon Power areas differ.

Accredited designer and installer, approved products

To claim STCs, the designer and installer must be accredited by Solar Accreditation Australia (SAA) and hold an unrestricted electrical licence in the state or territory of installation, according to the Clean Energy Regulator (CER). SAA took over accreditation from the Clean Energy Council on 29 May 2024. SAA accredits individuals, not companies, so ask for the accreditation number of the person who will install your system and check it with SAA. The panels and inverters must be on the Clean Energy Council (CEC) approved lists of modules and inverters when installed and before their listed expiry date. The CEC says its inverter list changes, with models removed and expiry dates brought forward, so check your quote's models against the current lists. The installer must attend the site for three stages: job setup, mid-installation check-up, and testing and commissioning.

Small-scale technology certificates

STCs are created by a registered agent if you assign your right to them, or by you. You cannot create them once you have assigned the right to an agent. They must be created within 12 months of installation, and they are assigned to a property address, not an owner. Second-hand systems are not eligible. To estimate your certificates, use our STC calculator.

Council and planning

According to energy.gov.au, most rooftop solar can be installed without planning approval, but there may be restrictions on size or how it is installed. Heritage-listed areas may have rules and need a development application. In the ACT most systems need no development approval. AusNet says that depending on where you live you may need planning approval from your local council. Your installer should know the rules for your area.

Larger and business systems

Small-scale solar means 100 kW or under. The CER says mid-scale solar from 100 kW to 1 MW applies to systems installed from 1 October 2026, and applications open mid to late November 2026. In the Northern Territory, systems above a 30 kW inverter follow a different process. This guide covers the residential and small business version of the steps. For larger sites, see commercial solar.

What happens on installation day

Installation day is mostly mounting, wiring and connecting the inverter, and it runs more smoothly if the installer has visited the site beforehand. This is the usual sequence from energy.gov.au:

  • The accredited installer arrives and there is paperwork to sign.
  • Panels, inverter and components are delivered, sometimes the day before.
  • Temporary safety railings go up on some roofs.
  • Metal rails are fixed to the roof and the panels are attached.
  • The inverter goes on a shaded external wall or in a garage close to the switchboard.
  • Cabling connects the panels to the inverter.
  • The inverter is connected to the switchboard and a circuit breaker is added.

On a tiled roof, installers cut or grind tiles to fit over the brackets so the roof does not leak. Tiles can be damaged even when the installer is careful, and they may ask you for spare tiles. A wet roof is slippery, so rain can delay the job. energy.gov.au says you should not be charged extra fees if installation is rescheduled due to rain. Try to be home for most of it, or make sure the installer can reach your switchboard and roof cavity. Have your Wi-Fi password handy for the monitoring set-up.

Handover checklist

Before you sign off, check these items, which come from energy.gov.au and the Clean Energy Regulator:

  • The installer has shown you how to switch the system on and off and how to read the display.
  • Monitoring is set up, if there is a monitoring app, and you have access.
  • You have seen the installer's accreditation and licence details.
  • The panels, inverter and any extras such as optimisers match your quote or contract.
  • Your installer has completed the compliance statement for the STC claim, and you have the certificate of electrical safety or the equivalent for your state or territory.
  • You have operating instructions, including the shutdown and isolation procedure.
  • You have warranty information for each product and for the installation.
  • You have the contract of sale, system specifications, maintenance advice and installer contact details.

For a fuller walk-through, use the solar panel inspection checklist. You can also run the installer's details through check my installer.

Your rebate, worked out to your address

Then one Why Solar Approved installer near you, and fifteen minutes with a solar expert before you sign.

Common installation problems

Most problems come from changes late in the process or from waiting on the network. Each has a practical fix.

  • Design changes between quote and installation. Network requirements, component availability or a site visit can change the design. Ask for any change, and its effect on cost or generation, in writing and agree it before installation.
  • Switchboard or meter board work found late. A site visit before the quote makes this less likely. Ask who does the work and when.
  • Smart meter delay. Do not switch the system on until you have confirmation that the meter is installed or configured.
  • Rain. Expect a delay if it rains all day, and ask that no extra fees apply.
  • Tiled roof damage. Ask how the installer handles tiles and if you need to supply spares.
  • Installer not on site for all three stages, or work subcontracted. The retailer may subcontract, but an SAA accredited installer must be on site for job setup, the mid-installation check-up and commissioning.
  • Components differ from the quote. Check the panels and inverter before they go on the roof.
  • Network limits on size or export. The connection agreement can limit inverter size or export. See solar export limits by state.
  • System not working, or damage. Contact the company that sold you the system in writing by email. If you are not satisfied, contact your state office of fair trading or consumer affairs body.

For what to check once the system is running, read common solar mistakes after installation. To choose an installer before you sign, see how to vet a solar installer.

FAQs

How long does solar installation take?

expand_more
The installation itself takes 1 to 3 days, depending on the size of the system and the complexity of the job, according to energy.gov.au. Switch-on can come later, because it waits for the network connection and the smart meter. A connection agreement can take up to 30 business days in some areas. No single timeline covers every state.

What are the steps in a solar installation?

expand_more
You choose an installer and agree a quote, then the network connection is applied for and any switchboard work is done. The system is installed, tested and commissioned, and the smart meter is installed or configured. You switch on once that is confirmed, and STCs are created. The order varies by state.

Do I need approval to install solar panels?

expand_more
You need approval from your distribution network before the system is switched on, and in most states before installation. Most rooftop solar needs no planning approval from government, but there may be restrictions, and heritage-listed areas may need a development application. Your installer should know the rules for your area.

Who lodges the network connection application?

expand_more
In most cases your retailer or installer lodges it with your network operator, according to energy.gov.au. Energex says the retailer or installer can apply for you, and Ausgrid says your installer manages the approval. In Victoria your retailer or installer lodges the network connection application before installation. After installation they lodge a Certificate of Electrical Safety with Energy Safe Victoria, which is a separate later step. In South Australia your retailer or installer lodges the SEG request form with SA Power Networks, and after approval it goes to your electricity retailer for metering.

When can I switch my solar on after installation?

expand_more
Wait for confirmation that your smart meter is installed or configured, then switch on as your retailer or installer tells you. You may also wait for an independent audit. In Queensland, Energex says the installer must leave the system switched off until the metering can measure export.

When are STCs created and who claims them?

expand_more
STCs can be created once the system is complete and able to produce electricity, within 12 months of installation. A registered agent creates them if you assign your right, or you can create them yourself. The installer who completes testing gives the written compliance statement to whoever creates them.

Do I need to be home during solar installation?

expand_more
energy.gov.au says to try to be home for most of the installation. If you cannot be, make sure the installer can reach your switchboard and roof cavity. Discuss decisions such as inverter placement in advance.

Sources

Checked on 27 October 2026.

Get a quote from a Why Solar Approved installer

We match you with one installer who has passed all six of our checks. You get one written quote, and a 15-minute call with one of our solar experts before you sign. Getting a quote through us is free, with no obligation to go ahead. Installers pay us a set fee for each introduction.

The next step

If you're considering solar panels or batteries for your home, Bec and the team can match you with one Why Solar Approved installer near you for a free written quote, and fifteen minutes with a solar expert before you sign.

Headshot of Bec Ramirez, Aussie Mum & Energy Expert at Why Solar

Written by

Bec Ramirez

Aussie Mum & Energy Expert

Helps families switch to solar with practical, real-world advice. Bec focuses on the financial side: rebates, bill savings and financing options, so everyday Australians can see real value from going solar.

If you have any questions about the information in this guide, email hello@whysolar.com.au or call +61 2 5657 6527.

More about Bec

Make Why Solar a preferred sourceWe'll appear more often in your Google Top StoriesAdds Why Solar to your Google preferred sources, so we show up more often in your Top Stories and AI Overviews.
Share with a mate
Up to $8,000+ in solar and battery rebates · Federal rebates step down in 47 daysSee how we calculate this