Solar Basics

Solar Export Limits in Australia: What Applies in Your State

Pole-mounted transformer in a suburban street with solar roofs behind

Your solar rebate, checked before you sign

By Bec Ramirez

8 min read

Find out what your home actually needs

There is no single national solar export limit. A basic limit of 5 kW per phase still applies at Energex and Ergon (5 kVA at Evoenergy), but many networks now offer or require a flexible limit, typically 1.5 kW up to 10 kW per phase. Fixed fallback limits are often 1.5 kW. Your own limit is in your connection approval.

Checked 1 November 2026.

What is a solar export limit?

A solar export limit is the maximum power your system can send back to the grid at any moment. Networks set it because local transformers and power lines have finite capacity: when many homes export at once, voltage rises, which can cause problems on that part of the network.

Your inverter enforces the limit automatically by reducing output, which is called curtailment. The curtailed energy is lost unless you use it at home or store it in a battery, so a system can look healthy while producing less than your panels could.

How much can I export?

It depends on your network. Many homes can export 5 kW per phase on a basic connection, or up to 10 kW per phase on a flexible connection when the network has room. Some areas are limited to 1.5 kW, and some allow no exports at all. The figure that counts is the one in your connection approval.

FactDetail
Basic limit still in use5 kW per phase at Energex and Ergon (basic connection); 5 kVA per phase at Evoenergy
Flexible limitsTypically 1.5 kW up to 10 kW per phase where offered (for example SA Power Networks, Endeavour, Essential, Energex, Ergon)
Fixed fallback limitsOften 1.5 kW (SA Power Networks, Endeavour Fixed Exports plan, Western Power, backstop-exempt Ausgrid systems)
Where your limit is writtenYour connection approval or Connection Contract
Checked1 November 2026

Find out what your home actually needs

Free, takes about two minutes, no obligation.

Export limits by state

Figures are defaults for new connections, taken from each network's published information. The last column shows when each row was last checked. Your approval can differ. "Check with the network" means we did not verify a figure.

StateNetworkFixed / basic limitFlexible optionSource date
NSWAusgrid3 kW fixed (1.5 kW if communications are lost); 1.5 kW static if backstop exempt1.5 to 10 kW single phase; 1.5 to 20 kW two phase; 1.5 to 30 kW three phase (max 10 kW per phase)NS194 Rev 5, 10 Sep 2026
NSWEndeavour Energy5 kW now; Fixed Exports plan 1.5 kW maxUp to 10 kW per phase most of the time; default for eligible new and upgraded systems from November 2026, phased in to February 20271 Nov 2026 (5 kW figure: May 2026 factsheet)
NSWEssential Energy5 kW, single phase and three phase; lower in some areasChoose 1.5 to 5 kW or 1.5 to 10 kW per phase, from November 20261 Nov 2026
VICCitiPower, Powercor, United EnergySome pre-approvals are 0 kWUp to 10 kW most of the time1 Nov 2026
VICAusNetLow or zero in some congested areas; 1.5 kW fixed per phase for some customersUp to 5 kW per phase for eligible customers otherwise limited to 1.5 kW fixed per phase1 Nov 2026
VICJemenaCheck with the networkCheck with the network20 Oct 2026
QLDEnergex5 kW per phase; none in some areasDynamic: 1.5 to 10 kW per phase1 Nov 2026
QLDErgon Energy5 kW per phase; 2 kW on regional single wire network; none in some areasDynamic: 1.5 to 10 kW per phase1 Nov 2026
SASA Power Networks1.5 kW per phase or 0 kW, by areaUp to 10 kW per phase1 Nov 2026
WAWestern Power1.5 kW unless the retailer can remotely disconnect and reconnect the systemCheck with the network1 Nov 2026 (WA Govt page updated 24 Feb 2026)
WAHorizon PowerCheck with the networkCheck with the network20 Oct 2026
TASTasNetworksCheck with the networkCheck with the network20 Oct 2026
ACTEvoenergy5 kVA per phaseCheck with the network1 Nov 2026
NTPower and WaterCheck with the networkCheck with the network20 Oct 2026

How flexible exports work

Flexible exports adjust your limit through an internet-connected inverter: with spare capacity you export more, and when the grid is congested the limit drops. Ergon's network signals the inverter every 5 minutes. A 12-month CitiPower and Powercor trial found customers had unrestricted exports more than 90% of the time. If the internet is lost for an extended period, Ergon's limit typically reverts to 1.5 kW, and SA Power Networks ramps exports down to 1.5 kW during an outage.

Queensland: Energex and Ergon areas

Energex's basic connection allows total inverter capacity of up to 10 kVA per phase and export of up to 5 kW per phase. Energex and Ergon both limit new systems up to 30 kVA to 5 kW per phase, or no exports in areas where too much solar could cause network issues. On Ergon's regional single wire network, the basic limit is 2 kW.

A dynamic connection allows up to 10 kW per phase when the network has spare capacity. When exports must be reduced, you still get at least 1.5 kW, unless a significant emergency event requires all generation to stop. Any customer can apply through their installer, though reduced dynamic export levels may apply where there is very high solar or limited network monitoring. See Queensland feed-in tariffs.

Victoria: AusNet and other networks

Victoria has no single statewide figure, so your network matters.

AusNet says some customers in congested areas now have low or zero export limits. Its flexible offer gives residential customers up to 5 kW per phase, depending on available yearly capacity. For now, it is limited to eligible customers who would otherwise be limited to a maximum of 1.5 kW fixed per phase, and AusNet says it is likely to extend to more customers. To ask about it, use the solar option on AusNet's Contact us page.

CitiPower, Powercor and United Energy customers who receive a 0 kW pre-approval can choose flexible exports or the 0 kW static limit. Flexible exports let you export to your inverter's limit, up to 10 kW, most of the time. Since October 2024, new installations in these areas need a Clean Energy Council approved inverter that supports CSIP-AUS. Devices that do not support it must be set to zero export. See Victorian feed-in tariffs.

NSW, WA and other networks

NSW

Essential Energy generally applies a fixed 5 kW limit, lower in some areas, and lets you apply for a higher limit, assessed on local network capacity. From November 2026, you can choose a flexible limit of 1.5 to 5 kW or 1.5 to 10 kW per phase on new and upgraded backstop-enabled systems up to 200 kW.

Endeavour Energy makes flexible exports the default for eligible new and upgraded systems from November 2026, rolling out in phases on 2 November 2026, in late November 2026 and in February 2027. You need internet, net export metering and a CSIP-AUS approved inverter.

Under the NSW Emergency Backstop Mechanism, new and upgraded systems up to 200 kW need CSIP-AUS compliant equipment and installer portal commissioning. Endeavour systems with a connection application submitted and approved from Monday 2 November 2026 must be commissioned through the portal. For Ausgrid and Essential Energy, the date is Monday 23 November 2026.

Ausgrid's key dates are below. These requirements are not for existing systems.

  • 23 November 2026: solar retailers register new and upgrading systems up to 200 kW in the CER Installer Portal.
  • 30 November 2026: the capability test is phased in by postcode.
  • 22 February 2027: all new and upgrading systems are registered and backstop-enabled.
  • 22 May 2027: systems approved before 23 November 2026 but not commissioned must reapply.

In Ausgrid's area, where a premises lacks reliable internet, a low static limit of 1.5 kW per site must be set until connectivity is available. See NSW feed-in tariffs.

WA

Since 1 May 2026, new and upgraded systems on Western Power's network must be remotely disconnectable and reconnectable by the retailer, or otherwise be export limited to 1.5 kW. Standard connections can install inverters up to 30 kVA. We have not verified the limit on the remote disconnection pathway, so confirm it with Western Power. See WA feed-in tariffs.

SA, ACT and others

SA Power Networks asks you to choose a fixed limit or Flexible Exports when you install a new inverter. Flexible Exports go up to 10 kW per phase, but some sites may never reach 10 kW and some may not export at all. See SA feed-in tariffs. Evoenergy applies 5 kVA per phase to all residential solar systems, and embedded networks may be less. For TasNetworks, Horizon Power, Jemena and Power and Water, check with the network.

What is a DNSP?

DNSP stands for distribution network service provider: the company that owns and runs the poles and wires in your area and approves solar connections and export limits. Examples include Ausgrid, Energex and Western Power. Your approved limit is written in your connection approval. Essential Energy puts it in the Schedule of Site-Specific Conditions in your Connection Contract.

Your rebate, worked out to your address

Then one Why Solar Approved installer near you, and fifteen minutes with a solar expert before you sign.

Single-phase connections vs three phase

Yes, your limit can differ by phase count, but there is no single multiplier. Energex, Ergon and SA Power Networks set limits per phase. Essential Energy generally applies a fixed 5 kW limit to both single-phase and three-phase systems. Ausgrid sets flexible limits by phase count, as the table shows, with a maximum of 10 kW per phase.

In Queensland, a static single-phase connection allows up to 10 kVA of inverter capacity and a fixed 5 kW export limit, or 10 kVA and 2 kW on a single wire connection. Under a fixed export connection, solar plus battery shares that 10 kVA. With a dynamic connection, you can install 10 kVA of solar plus 10 kVA of battery inverter capacity on single phase, which can avoid an upgrade to three phase. A hybrid inverter is still limited to 10 kVA in total.

Check your phase count at the switchboard or with an electrician. Where a limit is low, a bigger system is curtailed more often: try our solar calculator and read the oversized solar system guide.

Going over the limit

A correctly set inverter should not let your exports go over the limit, and Essential Energy is plain that limits should not be exceeded. If a network finds a non-compliant installation, it can notify the installer and customer, and may disconnect the system until it is fixed. Essential Energy, Energy Queensland and Evoenergy all flag disconnection as a possible outcome.

Be careful with changes after installation. Ergon says installers must not connect additional inverters, make modifications or add batteries unless a connection application has been submitted and an offer accepted.

The easiest fix is to get it right before you sign. Read our guide to sizing your system, and if a car is part of the plan, see how to size your solar system for EV charging. Already have a quote? Run it through our quote check and ask your installer what export limit it assumes.

Export limiters explained

An export limiter is not usually a separate gadget to think about. The limit is enforced by the inverter, typically fitted with an energy meter that measures what flows to the grid. The inverter then reduces output so exports stay under your approved figure.

On flexible exports, the network sends your limit to a CSIP-AUS inverter over the internet. Either way, curtailed energy is lost unless you use it at home or store it in a battery. Evoenergy also notes that if your inverter keeps switching off or reducing output, it is responding to changes in voltage.

Yes, in practice. Limits are conditions of your connection contract or agreement with the network, such as Essential Energy's Connection Contract or Energex's Model Standing Offer, not one national rule. Breaching them can lead to disconnection, as set out in the connection contract.

There is no single start date. Key dates for newer rules are:

  • Queensland: 6 February 2023 (Generation Signalling Device, for certain systems). From 23 February 2025, all low voltage inverters must comply with AS/NZS 4777.2:2020 and be installed to AS/NZS 4777.1:2024.
  • SA: 1 July 2023. Any exporting system installed from then must be Flexible Exports compatible.
  • Victoria: since October 2024, new installations in CitiPower, Powercor and United Energy areas need a CSIP-AUS inverter.
  • WA: 1 May 2026.
  • NSW: installer portal from 2 November 2026 (Endeavour) and 23 November 2026 (Ausgrid, Essential). Requirements roll out by network into 2027.

How to check and manage your connection

Start with your connection approval, or ask your installer to confirm your limit before you sign.

  • Find your Connection Contract or approval and its site-specific conditions.
  • Ask whether flexible exports are available, and whether to apply for a higher limit (Essential Energy accepts applications).
  • Confirm your phase count at the switchboard or with an electrician.
  • Check your inverter supports CSIP-AUS and has reliable internet.
  • Run the dishwasher or pool pump in the middle of the day, so less is exported.

Zero export

Some areas allow no exports at all: Energex and Ergon name areas where exports could cause network issues, AusNet has low or zero limits in some congested areas, Powercor and United Energy issue 0 kW pre-approvals, and SA Power Networks has 0 kW areas. Without a battery, surplus generation is wasted.

Batteries

A battery stores energy that would otherwise be curtailed. See our best solar batteries guide, battery options and inverter battery compatibility.

FAQ

What is a solar export limit, and what does DNSP stand for?

expand_more
A solar export limit is the most power your system can send to the grid at any moment. DNSP stands for distribution network service provider, the company that owns the poles and wires in your area and approves your connection. Your inverter enforces the limit by reducing output.

How much can I export to the grid?

expand_more
It depends on your network. Basic limits of 5 kW per phase apply at Energex and Ergon, and 5 kVA per phase at Evoenergy, while Essential Energy generally applies a fixed 5 kW. Where flexible exports are offered, limits typically run from 1.5 kW up to 10 kW per phase. Your connection approval states your figure.

What is the solar export limit in Queensland for Energex and Ergon?

expand_more
Energex and Ergon limit new systems up to 30 kVA to 5 kW per phase on a basic connection, or no exports in some areas. Ergon's regional single wire network has a 2 kW limit. A dynamic connection allows up to 10 kW per phase when the network has capacity, with a 1.5 kW minimum except in a significant emergency event.

What is the solar export limit in Victoria?

expand_more
Victoria has no single statewide figure. AusNet offers a flexible limit of up to 5 kW per phase to eligible customers who would otherwise be limited to 1.5 kW fixed per phase, and some congested areas have low or zero limits. CitiPower, Powercor and United Energy customers who receive a 0 kW pre-approval can choose a 0 kW static limit or flexible exports of up to 10 kW most of the time. For Jemena, check with the network.

Does a single-phase connection change my solar export limit?

expand_more
It can, but there is no single rule. Energex and Ergon set limits per phase, and a static single-phase connection there allows 10 kVA of inverter capacity and 5 kW of exports. With a dynamic connection, you can install 10 kVA of solar plus 10 kVA of battery inverter capacity on single phase, which can avoid an upgrade to three phase. Essential Energy generally applies a fixed 5 kW limit to both single-phase and three-phase systems.

What happens if I go over my solar export limit?

expand_more
A correctly set inverter should not let exports go over the limit. If a network finds a non-compliant installation, it can notify the installer and customer, and may disconnect the system until it is fixed. Adding a battery or changing inverters needs a new connection application first.

Are solar export limits legally binding, and when did the rules come in?

expand_more
Limits are conditions of your connection contract or agreement with the network, and breaching them can lead to disconnection. There is no single national start date. Newer rules came in on different dates, including Queensland on 6 February 2023, SA on 1 July 2023, parts of Victoria from October 2024 and WA on 1 May 2026. NSW installer portal requirements start from 2 and 23 November 2026, depending on the network.

What does an export limiter do?

expand_more
An export limiter keeps your exports under your approved figure. The inverter, typically fitted with an energy meter, measures what flows to the grid and reduces output when needed. On flexible exports, the network sends your limit to a CSIP-AUS inverter over the internet. Curtailed energy is lost unless you use it at home or store it in a battery.

How do I check my own solar export limit?

expand_more
Check your connection approval, such as the Schedule of Site-Specific Conditions in an Essential Energy Connection Contract, or ask your installer. Confirm your phase count at the switchboard or with an electrician, ask about flexible exports, and check your inverter supports CSIP-AUS. Essential Energy lets you apply for a higher limit, assessed on local capacity.
Sources

The next step

If you are considering solar panels or a battery, Bec and the team can match you with one Why Solar Approved installer near you for a free written quote, and fifteen minutes with a solar expert before you sign.

Headshot of Bec Ramirez, Aussie Mum & Energy Expert at Why Solar

Written by

Bec Ramirez

Aussie Mum & Energy Expert

Helps families switch to solar with practical, real-world advice. Bec focuses on the financial side: rebates, bill savings and financing options, so everyday Australians can see real value from going solar.

If you have any questions about the information in this guide, email hello@whysolar.com.au or call +61 2 5657 6527.

More about Bec

Make Why Solar a preferred sourceWe'll appear more often in your Google Top StoriesAdds Why Solar to your Google preferred sources, so we show up more often in your Top Stories and AI Overviews.
Share with a mate
Up to $8,000+ in solar and battery rebates · Federal rebates step down in 34 daysSee how we calculate this