EV Charger Installation

What it takes to install a home EV charger, from the electrical requirements to what happens on installation day and what it costs.

Installation guide. Costs are for the installation, on top of the charger.

The installation process

Five stages, usually done in a single visit.
  1. Site assessment

    Takes 15 to 30 mins

    An electrician inspects your switchboard, determines cable run length, and identifies the best charger location. They assess if any electrical upgrades are needed.

    Things to consider

    • Switchboard capacity check
    • Cable route planning
    • Wi-Fi signal strength
    • Charger mounting location
  2. Electrical upgrades (if needed)

    Takes 1 to 2 hours

    Some homes need switchboard upgrades to accommodate the additional load. This might include adding a dedicated circuit or upgrading the main switch.

    Things to consider

    • May add $300 to $800 to cost
    • Older homes more likely to need
    • Required for 3-phase chargers
    • Load management options available
  3. Cable installation

    Takes 1 to 3 hours

    Heavy-duty cabling is run from your switchboard to the charger location. This can be surface-mounted or concealed depending on your preference and budget.

    Things to consider

    • Longer runs cost more
    • Concealed looks better but costs more
    • Outdoor-rated cable for external runs
    • Conduit protection where needed
  4. Charger mounting

    Takes 30 to 60 mins

    The charger unit is securely mounted to the wall (or pedestal). The electrician ensures it is level, accessible, and positioned correctly for your vehicle.

    Things to consider

    • Wall mount most common
    • Pedestal option available
    • Consider cable reach to car
    • Height for easy use
  5. Connection and testing

    Takes 30 to 60 mins

    The charger is connected, configured to your preferences, and tested. You are shown how to use the charger, app setup, and any smart features.

    Things to consider

    • Full load test performed
    • App connected to Wi-Fi
    • Solar integration if applicable
    • Safety features demonstrated

Electrical requirements

  • Single Phase (7kW)

    Most Australian homes

    Power draw
    32 amps @ 240V
    Circuit
    Dedicated 40A circuit
    Charge speed
    40 to 50km range per hour
  • Single Phase (7.4kW)

    Standard installation

    Power draw
    32 amps @ 240V
    Circuit
    Dedicated 40A circuit
    Charge speed
    45 to 55km range per hour
  • Three Phase (11kW)

    Homes with 3-phase supply

    Power draw
    16 amps @ 415V
    Circuit
    Dedicated 3-phase circuit
    Charge speed
    65 to 75km range per hour
  • Three Phase (22kW)

    Large homes, multiple EVs

    Power draw
    32 amps @ 415V
    Circuit
    Dedicated 3-phase circuit
    Charge speed
    120 to 140km range per hour

Do you need three-phase? Usually not. Most EV owners are well served by a 7kW single-phase charger. It adds 40 to 50km of range an hour, plenty for overnight charging. Three-phase (11 to 22kW) is only needed if you drive very long distances daily or have more than one EV.

Where the charger can go

Garage wall

Popular choice

Good

  • Protected from weather
  • Secure
  • Clean installation
  • Easy cable management

Watch for

  • Requires garage space
  • Car must fit with cable
Installation costStandard

External wall

Popular choice

Good

  • Accessible from driveway
  • Doesn't use garage space
  • Good for carports

Watch for

  • Weather exposure
  • Less secure
  • May need weatherproof unit
Installation costStandard

Pedestal or bollard

Good

  • Flexible placement
  • Professional look
  • Good for shared spaces

Watch for

  • Higher cost
  • Ground works needed
  • Underground cabling
Installation cost+$500 to $1,500

Installation costs

Installation costs are in addition to the charger unit price. Most installs fall in the $600 to $1,200 range.
Simple install (garage, close to switchboard)Short cable run, no upgrades needed
$300 to $600
Standard install (up to 15m cable)Typical installation, minor works
$600 to $1,200
Complex install (long run, upgrades)Switchboard upgrade, long cable run
$1,200 to $2,500
Three-phase installationThree-phase circuit, professional install
$1,500 to $3,000

Most installs take a single visit